Packages available for tender in the next 3 months
- Miscellaneous metalworks – released
- Handrails and balustrades – released
- Metal furniture – released
- External furniture – August
- Painting stage 2 – August
- Exercise equipment – September
- Landscaping – September
- Wayfinding and statutory signage – October
To register your interest, please go to the creating new pathways page.
To date, the following major subcontractors have been appointed:
Package | Scope | Subcontractor |
Scaffolding | Ballina Scaffolding | |
Horizontal grouting | BCL Contractors | |
Precast panel connection welding | KWONS Engineering | |
Painting Stage 1 | Usher and Son Coatings | |
Concrete cutting and drilling | Stocks and Hogan | |
Kitchen and Laundry | T & H Sheetmetal | |
Joinery Stage 1 | Page Furnishers | |
Metal fencing works | Greg Wheeler Contracting | |
Ceilings and partitions | ICON Ceilings | |
Aluminium Doors and windows | Queensland Glass | |
Jailguard glass | Viridian Glass | |
Roofing and cladding | Red 8 Roofing | |
Roller shutters | Steel-line garage doors | |
Secure custodial door locks | Jackson Lock Manufacturing | |
Hydromulching | Spraygrass Landscapes | |
Large Trees | Great Gardens Landscaping | |
Cell Furniture | Worldwide Materials P/L | |
Precast perimeter fence installation | Advanced Fencing | |
Door Frames and Hardware | Zenith Doors P/L | |
Temporary/ Permanent In-Ground Services | Temporary/permanent Electrical, Hydraulic, Communications and Security inground infrastructure | Laser Plumbing and Electrical |
Mechanical Services | Design and Construction of Mechanical Services | Climatech NSW P/L |
Hydraulic Services | Design development, design finalisation and the construction of the Hydraulic Services | JR Keith P/L |
Wet and dry fire services | Full design, supply, install, configuration, testing, commissioning (including integrated commissioning) and handover training of the NGCC Fire Services | Triple M Fire P/L |
Stage 1 Bulk Earthworks & Stormwater | Mobilisation, Site Establishment Works, Erosion & Sediment Control Install, Permanent Detention Basin Construction, Demolition of Existing House/ Stockyards /Fencing, Stage 1 Bulk Earthworks & Stage 1 Stormwater Works | Ditchfield Contracting |
Water supply & water cart | Supply potable water and water cart for dust suppression | Jacques Earthmoving |
Fuel supply | Onsite fuel supply and equipment |
Caltex |
Site Accommodation | Site accommodation buildings, ablution blocks, |
Ausco |
Volumetric cell and pre-cast fence panels | Supply of pre-cast volumetric cells and fence panels | Civmec Construction |
Structural Steelworks | Supply & install structural steelwork | Hutchins Bros |
Rubbish removal & septic pumping | Skip bin supply, rubbish removal, septic servicing | JR Richards/ Clarence Valley Septics |
Chain Wire Fencing and Gates | Supply & installation of the Temporary and Permanent chain wire fencing and gates | Coffs Harbour Fencing |
Electronic Security Services | Design, supply, install, configuration, testing, commissioning (including integrated commissioning) and handover training of the NGCC Electronic Security Services system | SAAB Australia |
Construction Survey | Survey – Temporary Works, Site Works, Technical Completion and Commercial Acceptance Survey | Usher and Company Pty Ltd |
Form, Reo, Poor – Male Max/Female Max | Formwork, reinforcement supply and concrete pour | Manly Concrete |
Form, Reo, Poor – Male Min | Formwork, reinforcement supply and concrete pour | FJE & J Farlow |
Flat Panel Precast | Supply of flat panel precast panels | Austral Precast |
Lifts | Supply and installation of lifts in Building 3 and 14 | Kone Elevators |
Temporary Generator Hire | Hire of temporary generators during |
Onsite rental |
Site security guards | Provision of security services during construction phase | Marsters Entourage Security Solutions |
Site security cameras and monitoring | Supply, installation and monitoring of security cameras during construction phase | No 1 Protection Services |
Time-lapse photography | Supply and installation of time-lapse camera system during construction phase | Inception Time Lapse and Photography |
Site cleaning | Provision of site cleaning services | TJS Cleaning |
Concrete supply | Supply of concrete for the entire project including onsite batching plant | Hansen |
Permanent electrical works and ICT | Permanent electrical and ICT installations | Fredon |
Hydraulic Services | Hydraulic Services – including wet fire infrastructure services | Sedgman |
Fire Life Safety Engineering | Fire Life Safety Engineering consultant | PGA |
Secure Windows, Doors & Louvres | Supply of Secure Windows, Doors & Louvres | Locker Group |
More information on how to engage with major subcontractors will be made available later this year. To keep updated, please register your interest here.
Please note that all subcontractors in the construction phase are required to comply with the Building Code, and the Implementation Guidelines to the New South Wales Code of Practice for Procurement Building and Construction (NSW Code).
The Building Code is available at:
www.abcc.gov.au/building-code
The NSW Code is available at:
www.industrialrelations.nsw.gov.au